You are currently viewing Tarraleah & Tungatinah switchyard rebuild

Tarraleah & Tungatinah switchyard rebuild

PowerNet was happy to be awarded the electrical installation contract to carry out the construction works on behalf of the principal contractor Powercor Network Services.

The Primary rebuild took just over two years to complete and consisted of:

  • HV cable jointing & terminations 11kV
  • Installation of new towers and gantries
  • Overhead Al bus Stranded and Solid
  • Installation of new 110kV to 11kV TX
  • Stringing of 6 outgoing Transmission lines
  • 4 new 110kV CB
  • 23 new Disconnect switches
  • 13 new Earth Switches