These 220kV green field builds were in the South West of Victoria and constructed for renewable wind energy to connect to the grid via the 220kV Ballarat to Horsham line. PowerNet was engaged by Downer Group to perform the electrical installation and site management of;

  • 220kV primary and secondary works
  • 220kV Siemens CB assembly
  • 220kV GE ROI and Earth switch assembly
  • 250 and 48Vdc battery room install and discharge testing/comms
  • 220kV line cut in and tower modification coordination